Contractor Claiming Loss Of Profits Due To Delayed Execution Must Prove That Other Works Were Lost Due To Delay : Supreme Court


28 Sep 2023 5:21 AM GMT


Ongoing Enrollments:
Certificate Course in Labour Laws Certificate Course in Drafting of Pleadings Certificate Programme in Train The Trainer (TTT) PoSH Certificate course in Contract Drafting Certificate Course in HRM (Human Resource Management) Online Certificate course on RTI (English/हिंदी) Guide to setup Startup in India HR Analytics Certification Course

The Supreme Court Bench comprising Justice Sanjiv Khanna and Justice M.M. Sundresh, has held that in arbitral proceedings where the execution of a contract is delayed and the Contractor claims loss arising from depletion of income, then the Contractor must prove that there was alternative work available for him/her by placing on record invitation to tender, which were rejected by the...

%>